Skip to content
Skip to main content

About this free course

Download this course

Share this free course

Tay Bridge disaster
Tay Bridge disaster

Start this free course now. Just create an account and sign in. Enrol and complete the course for a free statement of participation or digital badge if available.

5.7 Fitment flaws

The secondary category of defects observed by Law and his team refer to defects of fitment of the columns and braces together during construction of the bridge. He noted many bolt holes had been deliberately enlarged, but why this was necessary remains unclear, especially as the bolts were 0.125 inch smaller than the holes. Perhaps burrs or points in the holes needed removal before the bolts would fit correctly. The quadrants also came in for criticism for their poor fit to the columns, and it is certainly true they usually failed here during the collapse (see Figures 27, 28, 32 and 35).

Table 6 Tay Bridge defects: fitment flaws
Fitment flawNumberWhere foundReference
1enlarged, damaged bolt holes formed during erection of piersmanye.g. P214,341
2quadrants for horizontal tie rods poorly fitted; metal only 0.5 inch thickmost14,593 12,638
3four bolts attaching L girders to pier heads, rather than eight1P214,609 12,651
4extra set of holes drilled in flange1P1, T1, C314,718
5poor adhesion between cement and masonry at pier basemany pierse.g. P9, C612,533
6base bolts poorly embeddedmany piers?12,565
7poor quality of cement in some columnsa few columns (?)?P6+12,876
8cement in jointa few columnsP5, 6 ,C112,694
9gibs/cotters poor fit: cotter compressed when tie bar strained2 cotters/gib only, 2 gibs/cotter OK14,374 12,619
10packing pieces used in tie bars by noble12 picked up from pier basese.g. P1, T1/2, C5/6, C5/3, 412,676

Footnotes  

Adapted from Law's evidence to BoT enquiry. References are to question number in transcript, from evidence-in-chief and cross-examination. P = pier, T = tier, C = column, ? = unknown

Isolated examples of poor flange joints were mentioned, especially in the context of the L girders at the pier heads. The L girders can be seen in Figures 34 and 36 just under the main girders of the bridge, with rivetted end plates. There were two such girders, each attaching the two sets of three tiers of columns, and one was found with only half the required set of bolts. Another flange joint had an extra set of holes drilled, presumably because of misalignment.

Although slag inclusions were apparently extensive, few if any are visible in the pictures. In addition, the metal was said to be ‘sluggish’, but it is not clear what defects were specifically produced in the columns.

Most columns were said to have poorly formed flange ends, but those visible in the pictures (for example Figure 26) appear reasonably flat. On the other hand, if cement could trickle through the joints, then fitment in some cases would have been faulty.

The foundations also came in for criticism, especially on those relatively few piers where the masonry had failed in the collapse, such as pier 5 (Figure 44) although not all foundations had failed like this (see Figure 45). Base bolts were found to be poorly embedded in the masonry, and the cement barely held the stones together. Some of the cement was apparently of poor quality, although there is rather little evidence of the problem. With one exception (Figure 32), the cement has broken cleanly (for example, in the column end in Figure 26, as one would expect for a brittle material.

Figure 44
Figure 44 Pier 5, looking north, showing tilting of masonry. The columns visible on the platform are from the most westerly tiers and have toppled to the east
Figure 45
Figure 45 Pier 4, looking north, showing intact masonry. Some columns have fallen to the west – those hanging down near the water – while others on the platform have tilted to the east

The joints in the many tie bars however, came in for sustained critical comment. The cotters in particular, fitted the slot rather poorly, and were held only by friction of metal against metal. It could easily loosen, as was observed by Mr Noble in his many attempts to tighten them after construction. He packed them with shims. But if this was so widespread a problem, was it not an indication of a design rather than a fitment problem?