Risk management

3.4 Using mathematical models

In certain cases it may be useful to aggregate the impact from multiple risks, with unrelated root causes, each with their own impact and probability. A common reason for doing this is on large projects to look at both potential schedule and financial impacts, and ensure that sufficient funds or contingency (time and money) are put aside to deal with the risks.

The approaches used to assess these risks can be quite advanced and are beyond the scope of this course. They are usually performed by experts using specialised computer packages. The information below outlines common approaches that you may come across.

Analysis typeDescription
Monte CarloA mathematical model (sometimes called a stochastic model) based on a repeated random sampling to obtain a numerical value. Results are numbers. ‘Simulations’ are then brought together to give a statistical probability of a particular outcome. Results are often presented as ‘p’ values, denoting how statistically likely a particular outcome is.
Strategic Review Analysis (SRA) or Programme Evaluation and Review Technique (PERT)This is an approach to understanding the likely variance to a schedule. Like the Monte Carlo, this is a mathematical simulation. Each task is typically give three values (often called a three-point estimate) where the values relate to Shortest, Longest and Expected time to complete. Multiple ‘iterations’ are then run to present the statistical probability of a particular outcome.
Expected Monetary Value (EMV)EMV is calculated by multiplying the impact of the risk by its likelihood. For example, if the impact of a risk is £10m and the likelihood is 50% then the EMV is 10 × 0.5 = £5m. This can be helpful if there is a group of independent (unrelated) risks where the impacts and likelihood are similar. This approach is often used for calculating contingency funds for projects. Care should be taken, however, where there is a small number of risks, where the risks are inter-related and where there is a number of large, but unlikely risks. Like most risk modelling it is recommended that you engage an expert.

It should be remembered that as with all calculations, these models are only as good as their inputs. Moreover calculations, if assumptions are not made clear, can be misleading. Often end users may not understand what a ‘p’ value is. Furthermore, the shape of the distribution may be important to understand, and, finally, people may believe that the output is more trustworthy simply because it has been put though a complicated model, irrespective of the quality of the underlying information.

RM_1

Take your learning further

Making the decision to study can be a big step, which is why you'll want a trusted University. The Open University has 50 years’ experience delivering flexible learning and 170,000 students are studying with us right now. Take a look at all Open University courses.

If you are new to University-level study, we offer two introductory routes to our qualifications. You could either choose to start with an Access module, or a module which allows you to count your previous learning towards an Open University qualification. Read our guide on Where to take your learning next for more information.

Not ready for formal University study? Then browse over 1000 free courses on OpenLearn and sign up to our newsletter to hear about new free courses as they are released.

Every year, thousands of students decide to study with The Open University. With over 120 qualifications, we’ve got the right course for you.

Request an Open University prospectus371